Schedule by Contested Case
Filing Deadline: Docket 6630-CE-316
Transcript- Objections to Proposed Corrections to Draft Transcript
Application of Wisconsin Electric Power Company for a Certificate of Public Convenience and Necessity to Construct and Operate the Paris Reciprocating Internal Combustion Engines Project, Consisting of Seven Natural Gas-Fired Reciprocating Internal Combustion Engines Generating up to 128 MW Total at the Lakeshore Capacity Improvement Project Regulator Station in the Town of Paris, Kenosha County, Wisconsin
Filing Deadline: Docket 137-CE-209
Offered Evidence Other- Exhibits Offered and Received at Hearing
Application of American Transmission Company LLC, as an Electric Public Utility, for a Certificate of Public Convenience and Necessity to Construct and Operate the Western Feed Transmission Line Project, Consisting of the Jupiter and Cosmos 345 kV Substations, Two Sets of Double-Circuit 345 kV Transmission Lines, One Set of Double-Circuit 138/345 kV, and One Single-Circuit 345 kV to Interconnect the New Jupiter and Cosmos Substations Located Primarily in the Villages of Yorkville and Mount Pleasant, Racine County, Wisconsin
Filing Deadline: Docket 137-CE-209
Offered Evidence Other- Revised Testimony
Application of American Transmission Company LLC, as an Electric Public Utility, for a Certificate of Public Convenience and Necessity to Construct and Operate the Western Feed Transmission Line Project, Consisting of the Jupiter and Cosmos 345 kV Substations, Two Sets of Double-Circuit 345 kV Transmission Lines, One Set of Double-Circuit 138/345 kV, and One Single-Circuit 345 kV to Interconnect the New Jupiter and Cosmos Substations Located Primarily in the Villages of Yorkville and Mount Pleasant, Racine County, Wisconsin
Filing Deadline: Docket 137-CE-209
Offered Evidence Other- Witness Verification Affidavits
Application of American Transmission Company LLC, as an Electric Public Utility, for a Certificate of Public Convenience and Necessity to Construct and Operate the Western Feed Transmission Line Project, Consisting of the Jupiter and Cosmos 345 kV Substations, Two Sets of Double-Circuit 345 kV Transmission Lines, One Set of Double-Circuit 138/345 kV, and One Single-Circuit 345 kV to Interconnect the New Jupiter and Cosmos Substations Located Primarily in the Villages of Yorkville and Mount Pleasant, Racine County, Wisconsin
Filing Deadline: Docket 5820-DR-100
Offered Evidence Other
Comments on the Commission staff Memorandum
Verified Petition of Superior Water, Light and Power Company for a Declaratory Ruling or, in the alternative, for Approvals of a Holding Company Takeover
Filing Deadline: Docket 137-CE-209
Transcript- Proposed Corrections to Draft Transcript
Application of American Transmission Company LLC, as an Electric Public Utility, for a Certificate of Public Convenience and Necessity to Construct and Operate the Western Feed Transmission Line Project, Consisting of the Jupiter and Cosmos 345 kV Substations, Two Sets of Double-Circuit 345 kV Transmission Lines, One Set of Double-Circuit 138/345 kV, and One Single-Circuit 345 kV to Interconnect the New Jupiter and Cosmos Substations Located Primarily in the Villages of Yorkville and Mount Pleasant, Racine County, Wisconsin
Filing Deadline: Docket 6630-CE-316
Brief- Initial Brief
Application of Wisconsin Electric Power Company for a Certificate of Public Convenience and Necessity to Construct and Operate the Paris Reciprocating Internal Combustion Engines Project, Consisting of Seven Natural Gas-Fired Reciprocating Internal Combustion Engines Generating up to 128 MW Total at the Lakeshore Capacity Improvement Project Regulator Station in the Town of Paris, Kenosha County, Wisconsin
Filing Deadline: Docket 137-CE-209
Transcript- Objections to Proposed Corrections to Draft Transcript
Application of American Transmission Company LLC, as an Electric Public Utility, for a Certificate of Public Convenience and Necessity to Construct and Operate the Western Feed Transmission Line Project, Consisting of the Jupiter and Cosmos 345 kV Substations, Two Sets of Double-Circuit 345 kV Transmission Lines, One Set of Double-Circuit 138/345 kV, and One Single-Circuit 345 kV to Interconnect the New Jupiter and Cosmos Substations Located Primarily in the Villages of Yorkville and Mount Pleasant, Racine County, Wisconsin
Filing Deadline: Docket 137-CE-209
Brief- Initial Brief
Application of American Transmission Company LLC, as an Electric Public Utility, for a Certificate of Public Convenience and Necessity to Construct and Operate the Western Feed Transmission Line Project, Consisting of the Jupiter and Cosmos 345 kV Substations, Two Sets of Double-Circuit 345 kV Transmission Lines, One Set of Double-Circuit 138/345 kV, and One Single-Circuit 345 kV to Interconnect the New Jupiter and Cosmos Substations Located Primarily in the Villages of Yorkville and Mount Pleasant, Racine County, Wisconsin
Filing Deadline: Docket 5780-TE-111
Offered Evidence Direct- Intervenor and Commission Staff
Application of City of Sturgeon Bay, as an Electric Public Utility, Door County, Wisconsin, for Approval of Revisions to its Parallel Generation Tariff
Filing Deadline: Docket 137-CE-212
Offered Evidence Direct- Applicant
Application of American Transmission Company LLC, as an Electric Public Utility, for a Certificate of Public Convenience and Necessity to Construct and Operate the Mill Road-Granville Transmission Line Project, Consisting of Two New 138 kV Transmission Lines, Rebuilding Two Existing Double-Circuit 345/138 kV Transmission Lines, and Constructing the 345 kV Mill Road Substation Located Primarily in the City of Milwaukee, Milwaukee County, and the City of Brookfield and the Village of Menomonee Falls, Waukesha County, Wisconsin
Filing Deadline: Docket 6630-CG-140
Offered Evidence Rebuttal- Parties and Commission Staff
Application of Wisconsin Electric Power Company for a Certificate of Authority under Wis. Stat. § 196.49 and Wis. Admin. Code § PSC 133.03 to Construct a New Liquefied Natural Gas Facility and Associated Natural Gas Pipelines in the City of Oak Creek, Milwaukee County, Wisconsin
Filing Deadline: Docket 5820-DR-100
Offered Evidence Other
Comments on the Commission staff Memorandum
Verified Petition of Superior Water, Light and Power Company for a Declaratory Ruling or, in the alternative, for Approvals of a Holding Company Takeover
Filing Deadline: Docket 6630-CE-317
Offered Evidence Surrebuttal- Parties and Commission Staff
Application of Wisconsin Electric Power Company for a Certificate of Public Convenience and Necessity to Construct and Operate the South Oak Creek Combustion Turbine Project, Consisting of Five Natural Gas-Fired Single-Cycle Combustion Turbines Generating up to 1100 MW total at the South Oak Creek Facility in the City of Oak Creek, Milwaukee County, Wisconsin
Filing Deadline: Docket 137-CE-209
Brief- Reply Brief
Application of American Transmission Company LLC, as an Electric Public Utility, for a Certificate of Public Convenience and Necessity to Construct and Operate the Western Feed Transmission Line Project, Consisting of the Jupiter and Cosmos 345 kV Substations, Two Sets of Double-Circuit 345 kV Transmission Lines, One Set of Double-Circuit 138/345 kV, and One Single-Circuit 345 kV to Interconnect the New Jupiter and Cosmos Substations Located Primarily in the Villages of Yorkville and Mount Pleasant, Racine County, Wisconsin
Filing Deadline: Docket 6630-CE-317
Offered Evidence Other- Errata Testimony and Replacement Exhibits
Application of Wisconsin Electric Power Company for a Certificate of Public Convenience and Necessity to Construct and Operate the South Oak Creek Combustion Turbine Project, Consisting of Five Natural Gas-Fired Single-Cycle Combustion Turbines Generating up to 1100 MW total at the South Oak Creek Facility in the City of Oak Creek, Milwaukee County, Wisconsin
Filing Deadline: Docket 5780-TE-111
Offered Evidence Rebuttal- Parties and Commission Staff
Application of City of Sturgeon Bay, as an Electric Public Utility, Door County, Wisconsin, for Approval of Revisions to its Parallel Generation Tariff
Filing Deadline: Docket 6630-CE-316
Brief- Reply Brief
Application of Wisconsin Electric Power Company for a Certificate of Public Convenience and Necessity to Construct and Operate the Paris Reciprocating Internal Combustion Engines Project, Consisting of Seven Natural Gas-Fired Reciprocating Internal Combustion Engines Generating up to 128 MW Total at the Lakeshore Capacity Improvement Project Regulator Station in the Town of Paris, Kenosha County, Wisconsin
Filing Deadline: Docket 6630-CE-317
Transcript- Draft Transcript
Application of Wisconsin Electric Power Company for a Certificate of Public Convenience and Necessity to Construct and Operate the South Oak Creek Combustion Turbine Project, Consisting of Five Natural Gas-Fired Single-Cycle Combustion Turbines Generating up to 1100 MW total at the South Oak Creek Facility in the City of Oak Creek, Milwaukee County, Wisconsin
Filing Deadline: Docket 9827-CE-100
Offered Evidence Direct- Applicant
Application of Badger Hollow Wind Farm LLC for a Certificate of Public Convenience and Necessity to Construct a Wind Electric Generation Facility Capable of Generating Up to 118 MW, a Collector Substation, and a 345 kV Generator Tie Line in the Towns of Clifton, Eden, Linden, Mifflin, and Wingville in Iowa and Grant Counties, Wisconsin
Filing Deadline: Docket 6630-CE-317
Offered Evidence Other- Exhibits Offered and Received at Hearing
Application of Wisconsin Electric Power Company for a Certificate of Public Convenience and Necessity to Construct and Operate the South Oak Creek Combustion Turbine Project, Consisting of Five Natural Gas-Fired Single-Cycle Combustion Turbines Generating up to 1100 MW total at the South Oak Creek Facility in the City of Oak Creek, Milwaukee County, Wisconsin
Filing Deadline: Docket 6630-CE-317
Offered Evidence Other- Revised Testimony
Application of Wisconsin Electric Power Company for a Certificate of Public Convenience and Necessity to Construct and Operate the South Oak Creek Combustion Turbine Project, Consisting of Five Natural Gas-Fired Single-Cycle Combustion Turbines Generating up to 1100 MW total at the South Oak Creek Facility in the City of Oak Creek, Milwaukee County, Wisconsin
Filing Deadline: Docket 6630-CE-317
Offered Evidence Other- Witness Verification Affidavits
Application of Wisconsin Electric Power Company for a Certificate of Public Convenience and Necessity to Construct and Operate the South Oak Creek Combustion Turbine Project, Consisting of Five Natural Gas-Fired Single-Cycle Combustion Turbines Generating up to 1100 MW total at the South Oak Creek Facility in the City of Oak Creek, Milwaukee County, Wisconsin
Filing Deadline: Docket 6630-CE-317
Transcript- Proposed Corrections to Draft Transcript
Application of Wisconsin Electric Power Company for a Certificate of Public Convenience and Necessity to Construct and Operate the South Oak Creek Combustion Turbine Project, Consisting of Five Natural Gas-Fired Single-Cycle Combustion Turbines Generating up to 1100 MW total at the South Oak Creek Facility in the City of Oak Creek, Milwaukee County, Wisconsin
Filing Deadline: Docket 5780-TE-111
Offered Evidence Surrebuttal- Parties and Commission Staff
Application of City of Sturgeon Bay, as an Electric Public Utility, Door County, Wisconsin, for Approval of Revisions to its Parallel Generation Tariff
Filing Deadline: Docket 9828-CE-100
Offered Evidence Rebuttal- Parties and Commission Staff
Application of Whitewater Solar, LLC for a Certificate of Public Convenience and Necessity to Construct a 180 MW Photovoltaic Electric Generation Facility Consisting of a Project Substation, 138 kV Generator Tie Line, 34.5 kV Collector Circuit, Inverters, and Other Associated Facilities, Located Within the City of Whitewater and Township of Cold Spring, Jefferson County, and the Townships of Whitewater and LaGrange, Walworth County, Wisconsin
Filing Deadline: Docket 6630-CE-317
Transcript- Objections to Proposed Corrections to Draft Transcript
Application of Wisconsin Electric Power Company for a Certificate of Public Convenience and Necessity to Construct and Operate the South Oak Creek Combustion Turbine Project, Consisting of Five Natural Gas-Fired Single-Cycle Combustion Turbines Generating up to 1100 MW total at the South Oak Creek Facility in the City of Oak Creek, Milwaukee County, Wisconsin
Filing Deadline: Docket 5780-TE-111
Offered Evidence Other- Errata Testimony and Replacement Exhibits
Application of City of Sturgeon Bay, as an Electric Public Utility, Door County, Wisconsin, for Approval of Revisions to its Parallel Generation Tariff
Filing Deadline: Docket 6630-CG-140
Offered Evidence Surrebuttal- Parties and Commission Staff
Application of Wisconsin Electric Power Company for a Certificate of Authority under Wis. Stat. § 196.49 and Wis. Admin. Code § PSC 133.03 to Construct a New Liquefied Natural Gas Facility and Associated Natural Gas Pipelines in the City of Oak Creek, Milwaukee County, Wisconsin